A dialogue conference was carried out in Aukra on 21 May, with announcement 12.5.2015. Participation was voluntary and not obligatory for participation in the competition.
This notice concerns the pre-qualification of participants for a price and design contest with collaboration and the subsequent turnkey contract.
Estimated project costs include VAT: 246 600 000 NOK (The project cost includes costs beyond the contract cost for the building. Also includes margins and reserves)
Area of new building — approx. 5 600 m² GFA
The project shall be completed 24.4.2018.
Deadline for submitting documentation for pre-qualification: 10.6.2015, 10:00.
Work schedule
Invitation to pre-qualified tenderers 19.6.2015
Dispatch of the tender documentation 31.8.2015
Tender seminar 9.9.2015
Tender deadline 11.1.2016
Contracting 20.1.2016
Collaboration period 1.2.2016-10.6.2016
Planned construction start 3.10.2016
Completion of building works 24.4.2018.