Short description
Helen Ltd is constructing a Bio Heat Plant with a fuel heat input of 220 MW. The main fuel will be wood based biomass. The procurement consists of a biomass boiler plant based on Circulating Fluidized Bed (CFB) technology, flue gas condensing plant, auxiliary equipment and boiler house. The procurement consists of 2 parts, which may be quoted as following:
— Alternative A (parts quoted separately):
1) Boiler Plant;
2) Flue Gas Condensing Plant.
— Alternative B (parts quoted together): boiler plant and flue gas condensing plant.
The candidate may send the application to tender for part 1 or/and part 2. The candidate may send the application for alternative B but must then apply and tender for both parts 1 and 2, too. The candidate shall fulfill the requirements for parts 1 and 2 to be qualified for alternative B. The supplier or suppliers will be chosen in the final evaluation. The economically most advantageous quotation or combination of the quotations will be chosen.