A prior information notice related to contract 62/2017; a Turnkey contract for a new transmission line Skullerud-Enebakkveien.
A 3 300 metres long tunnel from Skullerud Water Treatment Plant to Klemetsrud shall be constructed. The tunnel shall include a new water pipe with a dimension of 1.0 m.
The turnkey contract includes all works related to the construction of a tunnel and pipelines, including safety measures for the construction area, blasting, masses, ground works, water pipe works, commissioning, etc.
The completion is expected by 2021.
The qualification documentation will be published in January 2018.