Årstad sixth form college, Building A approx. 6 900 m2 gross shall be renovated.
New floor layout, new windows, insulation for the facade, new ceilings, new floor covers, new doors, new kitchen, new lift. All the technical installations shall be demolished and new installations shall be established.
The project is organised as a turnkey contract divided into two, one for construction and one for the technical professions. An interaction phase will be held before the final contract after the winners of the 2 contracts have been selected.
This turnkey contract is for construction.
Progress
The tender documents will be sent out in week 27/2014
Site survey 10.7.2014.
Tender deadline 15.9.2014.
Contracting 6.10.2014.
interaction phase 6th October – 8th December 2014.
construction start 7.4.2015.
Completion 27.6.2016.
Requests for the documents and all questions about the enquiry are to be sent to emailt: kjell.kvam@faveoprosjektledelse.no