Short description
I/S Vestforbrænding (hereinafter ’VF’) hereby calls for tenders for to build new compression heat pumps located at Vestforbrænding, Ejby Mosevej 219, 2600 Glostrup, Denmark, as a part of a carbon capture project divided into several lots. The heat pumps are specified as Lot 6A. VF wishes to engage a contractor for the engineering, installation, and commissioning of the heat pump system.
The heat pumps will be implemented as part of the second stage of flue gas condensation to guarantee that the flue gas is at 35 °C at the flue gas condensation outlet before entering an up-and-coming carbon capture plant. The first stage of the flue gas condensation, i.e., Lot 6B, is necessary to be implemented before Lot 6A, because existing absorption heat pumps must be decommissioned.
On the cold side, the heat pumps will be cooling an intermediate circuit, while on the hot side, will be preheating district heating water before entering the turbine condensers.