New access road between the existing county road 410 and Arendal Harbour, with the accompanying foot and cycle path on part of the stretch. Two new roundabouts, alterations to existing adjoining roads, foot and cycle culvert, and a bridge with a road and foot/cycle path.
Some alterations to the water and sewage and electricity/tele cables will be required in the project.
The concrete bridge is included as part of the contract, but will be executed as a turnkey contract.
The engineering design services are model based, and the follow-up of the project will be via professional models and upgrades to the drawings that exist as offer drawings. Detailed drawings in addition to the tender drawings must be produced by the contractor.