Assignment text
Executing of concrete foundations works, delivery of sub enterprise and calculating of correct foundation by use of the results of the Geological feasibility studies carried out by Energinet, at the new 150 km long double circuit 400 kV overhead line Endrup-Idomlund and Endrup-German Border, Jutland, Denmark The tender is divided into 5 lots. Each lot has between 81 and 98 foundations, and between 26.8 km and 32.7 km length.