Short description
The contracts comprise asphalting works on Europe and National roads in the 'Vestfold and Telemark' and 'Agder' Counties.
This notice covers 5 contracts. In the contracts approx. 75,000 tonnes of asphalt will be laid, and approx. 620,000 m2 of asphalt milled off. The largest contract covers the production and laying of approx. 20,000 tonnes of asphalt, while the smallest contract concerns the production and laying of approx. 9,000 tonnes.
The works shall be carried out in the period 25 April to 1 October 2022. except for "Telemark 2" here, the deadline is 14 - October 2022.