Norite gauti panašią informaciją kas rytą? Registruokitės 7 dienų NEMOKAMAI Mercell versijai!
Annual Construction/Erection All Risks policy including Marine Cargo, LEG3-06, extended Maintenance and Third-Party Liability insurance with inception from 1st March 2024.
Lot details:
Contract value Onshore max. DKK 300,000,000 per project (incl. fire and storm)
Ad hoc and planned Offshore cable, fibre and/or gas pipeline maintenance, reestablishment and repair works. Maximum limit per repair project DKK 150 mill.
Existing Property: Coverage will basically be 25% of the Contract value per project, min. DKK 50,000,000 and further limits according to the Schedule in the Risk & Insurance Information
document. Marine cargo DKK 25,000,000 + 10%, LEG3/06 DKK 50,000,000, extended maintenance period 60 months, Third-Party Liability insurance DKK 50,000,000 per project.
Option: CPL insurance: Onshore DKK 5,000,000 and Offshore DKK 25,000,000 per project.
Please refer to tender materials for more information.