Hankintapäätös
DTU is establishing the DTU Electromagnetic Test Centre (DTU ETC) for high-accuracy testing of antennas, components and circuits, as well as materials and scattering structures. The DTU ETC will comprise several laboratories in the existing building 353 and a new building 357. Phase I of the DTU ETC was initiated in 2016 and completed in 2018, while phase II was initiated in 2017 and will be completed in 2022.
This procurement includes the following 3 different test facilities:
— millimetre-wave antenna test facility;
— millimetre-wave component and circuit test facility;
— multipurpose antenna test facility.
The tender covers the above-mentioned three facilities, but so far DTU has only signed contracts for the first two. For the third facility/lot, DTU has finalized the evaluation and awarded the contract, but it is uncertain whether a contract can be signed. Once this is clarified DTU will publish an additional contract award notice covering the third/last lot.