Assignment text
Volumes of construction works:
• construction of a new reinforced concrete sewage pumping station — building area 650 m
• construction of reinforced concrete channel 2 500 x 1 800 mm – total 161.5 m, construction of GRP sewage gravity pipe DN1600 mm – total 21 m, construction of 2 pcs steel sewage pressure pipes OD1422 mm – total 271 m, construction of transformer substation;
• dismantling of the existing sewage pumping station;
• reconstruction of gas supply, dismantling of existing gas supply – total 40 m.